Queens General Site Work (QG-614MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This multisite contract will reconstruct pavements, fencing, drainage, play equipment, ballfields and miscellaneous site work in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2013
Projected Completion Date: March 2014
Completion Date: February 2015

Procurement

Start Date: February 2015
Projected Completion Date: November 2015
Completion Date: July 2016

Construction

Start Date: August 2016
Projected Completion Date: July 2017
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $2,253,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 10/11/2024