Queens General Site Work (QG-514MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Triborough Playground A; the sidewalks at Triborough Playgrounds A, B, C, and D; and the basketball courts and multipurpose play area at Hoyt Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2013
Projected Completion Date: June 2014
Completion Date: September 2014

Procurement

Start Date: September 2014
Projected Completion Date: June 2015
Completion Date: July 2015

Construction

Start Date: October 2015
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $1,975,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

  • Hoyt Playground, Queens
    Hoyt Av, 29 To 31 Sts
    Community Board: 01
  • Park, Queens
    Triborough Bridge Playground Hoyt Ave between Astoria Park to 31st Street.
  • Triborough Bridge Playground A Hoyt Ave between 21st and Astoria Park.
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024