Brownsville Recreation Center Pool Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof at Brownsville Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: January 2014
Projected Completion Date: January 2014
Completion Date: March 2014

Procurement

Start Date: March 2014
Projected Completion Date: December 2014
Completion Date: July 2015

Construction

Start Date: August 2015
Projected Completion Date: August 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $4,199,000
Funding Sources:
  • City Council
  • Mayoral

Location

Brownsville Playground, Brooklyn
Linden Boulevard and Mother Gaston Boulevard
Community Board: 16

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project