Brownsville Recreation Center Pool Roof Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the roof at Brownsville Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: January 2014
Projected Completion Date:
January 2014
Completion Date:
March 2014
Procurement
Start Date: March 2014
Projected Completion Date:
December 2014
Completion
Date:
July 2015
Construction
Start Date: August 2015
Projected Completion Date:
August 2017
Completion Date: June 2017