Citywide Public Restroom Building and Facility Reconstruction (CNYG-814MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct public restroom buildings and facilities at various parks and recreation locations citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2013
Projected Completion Date: December 2013
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: June 2015
Completion Date: March 2016

Construction

Start Date: May 2016
Projected Completion Date: May 2019
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $1,865,000
Funding Source: Mayoral

Locations

  • Bayview Playground, Brooklyn
    S/s Seaview Av Opp E 99 St
    Community Board: 18
  • El Shabazz Playground, Brooklyn
    Reid Av, Macon and Macdonough Sts
    Community Board: 03
  • People's Park, Bronx
    E. 141 St. bet. Brook Ave. and St Ann's Ave.
    Community Board: 01
  • Walter Gladwin Park, Bronx
    Cross Bronx Expressway, Third Avenue, Tremont & Arthur Avenues
    Community Board: 06
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 10/11/2024