Citywide Electrical Systems Reconstruction (CNYG-914M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct electrical systems at public restroom buildings and other park facilities citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2013
Projected Completion Date: January 2014
Completion Date: February 2014

Procurement

Start Date: February 2014
Projected Completion Date: November 2014
Completion Date: July 2015

Construction

Start Date: March 2016
Projected Completion Date: March 2019
Completion Date: March 2019

Understand how we build parks.

Funding

Total Funding: $215,000
Funding Source: Mayoral

Locations

  • Bayview Playground, Brooklyn
    S/s Seaview Av Opp E 99 St
    Community Board: 18
  • El Shabazz Playground, Brooklyn
    Reid Av, Macon and Macdonough Sts
    Community Board: 03
  • People's Park, Bronx
    E. 141 St. bet. Brook Ave. and St Ann's Ave.
    Community Board: 01
  • Sumner Playground, Brooklyn
    M Garvey Blvd, Throop, Park & Myrtle Avs
    Community Board: 03
  • Walter Gladwin Park, Bronx
    Cross Bronx Expressway, Third Avenue, Tremont & Arthur Avenues
    Community Board: 06
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project