Citywide Pool Electrical Systems Reconstruction (CNYG-614M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct deteriorated electrical systems at various pools citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: December 2013
Projected Completion Date:
December 2013
Completion Date:
February 2014
Procurement
Start Date: February 2014
Projected Completion Date:
November 2014
Completion
Date:
July 2015
Construction
Start Date: October 2015
Projected Completion Date:
October 2018
Completion Date: October 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Location
Betsy Head Park, Brooklyn
Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
Community Board: 16
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025