Citywide Pool Plumbing Systems Reconstruction (CNYG-714M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct deteriorated plumbing systems at pools citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2013
Projected Completion Date:
December 2013
Completion Date:
February 2014
Procurement
Start Date: February 2014
Projected Completion Date:
November 2014
Completion
Date:
March 2015
Construction
Start Date: April 2015
Projected Completion Date:
April 2018
Completion Date: April 2018
Understand how we build parks.
Funding
Funding Source: Mayoral
Locations
-
Betsy Head Park, Brooklyn
Blake Avenue, Dumont Avenue, Livonia Avenue between Strauss Street, Hopkinson Avenue and Bristol Street
Community Board: 16 -
Bushwick Playground, Brooklyn
Flushing Ave. between. Beaver St. and Garden St.
Community Board: 01 -
Flushing Meadows Corona Park, Queens
Grand Central Parkway, Van Wyck Expressway
Community Board: 03, 04, 06, 07, 08 -
John Jay Park, Manhattan
East 76-East 78 Streets, Cherokee Place
Community Board: 08 -
McCarren Park, Brooklyn
N. 12 St., Lorimer St., Manhattan Ave. bet. Bayard St. and Berry St. - Nassau Ave.
Community Board: 01 -
Van Cortlandt Park, Bronx
Broadway, Jerome Avenue, City Line, Van Cortlandt Park South
Community Board: 07, 08, 12
Project Staff
Project Liaison: Cristin Leoutsakos
Contact NYC Parks
about this project
Last updated: 01/17/2025