East River Park East 6th Street Synthetic Turf Soccer Field & Running Track Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the synthetic turf soccer field and resurface the running track in East River Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2013
Projected Completion Date: March 2015
Completion Date: November 2016

Procurement

Start Date: November 2016
Projected Completion Date: August 2017
Completion Date: July 2017

Construction

Start Date: September 2017
Projected Completion Date: September 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $3,076,000
Funding Sources:
  • Borough President
  • City Council

Location

John V. Lindsay East River Park, Manhattan
East 6th Street and East River Park
Community Board: 03

 