Crotona Par Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building at Playground of the Stars in Crotona Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2014
Projected Completion Date:
November 2015
Completion Date:
March 2018
Procurement
Start Date: March 2018
Projected Completion Date:
December 2018
Completion
Date:
February 2019
Construction
Start Date: September 2019
Projected Completion Date:
March 2021
Completion Date: June 2021
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Location
Crotona Park, Bronx
Franklin Avenue and Crotona Park South
Community Board: 03
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024