Crotona Par Public Restroom Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the public restroom building at Playground of the Stars in Crotona Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2014
Projected Completion Date: November 2015
Completion Date: March 2018

Procurement

Start Date: March 2018
Projected Completion Date: December 2018
Completion Date: February 2019

Construction

Start Date: September 2019
Projected Completion Date: March 2021
Completion Date: June 2021

Understand how we build parks.

Funding

Total Funding: $1,373,000
Funding Sources:
  • City Council
  • Mayoral

Location

Crotona Park, Bronx
Franklin Avenue and Crotona Park South
Community Board: 03

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 10/11/2024