Cedar Playground Public Restroom Building Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the public restroom building in Cedar Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2014
Projected Completion Date:
November 2015
Completion Date:
August 2016
Procurement
Start Date: August 2016
Projected Completion Date:
May 2017
Completion
Date:
May 2018
Construction
Start Date: July 2018
Projected Completion Date:
January 2020
Completion Date: October 2020
Understand how we build parks.
Funding
Funding Source: Borough President
Location
Cedar Playground, Bronx
Cedar Avenue between West 179th Street and Sedgwick Avenue
Community Board: 05
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024