Sumner Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Sumner Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2013
Projected Completion Date: December 2014
Completion Date: September 2015

Procurement

Start Date: September 2015
Projected Completion Date: June 2016
Completion Date: January 2017

Construction

Start Date: April 2017
Projected Completion Date: September 2018
Completion Date: October 2018

Understand how we build parks.

Funding

Total Funding: $5,045,000
Funding Sources:
  • City Council
  • Mayoral

Location

Sumner Playground, Brooklyn
Throop Avenue between Park Avenue and Myrtle Avenue
Community Board: 03

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024