Sumner Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct Sumner Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2013
Projected Completion Date:
December 2014
Completion Date:
September 2015
Procurement
Start Date: September 2015
Projected Completion Date:
June 2016
Completion
Date:
January 2017
Construction
Start Date: April 2017
Projected Completion Date:
September 2018
Completion Date: October 2018