Brooklyn Sandy-Related Tree Replacement

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will replace trees removed due to Hurricane Sandy damage in Brooklyn.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2013
Projected Completion Date: December 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: July 2014

Construction

Start Date: December 2014
Projected Completion Date: November 2015
Completion Date: November 2015

Understand how we build parks.

Funding

Total Funding: $2,450,000
Funding Sources:
  • Federal
  • Mayoral

Location

Various locations, Brooklyn