Queens Sandy-Related Tree Removal - Community Boards 1-5

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will remove trees damaged from Hurricane Sandy in Community Boards 1 through 5 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2013
Projected Completion Date: December 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: July 2014

Construction

Start Date: July 2014
Projected Completion Date: July 2015
Completion Date: August 2015

Understand how we build parks.

Funding

Total Funding: $1,000,000
Funding Sources:
  • Federal
  • Mayoral

Location

Various locations, Queens

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024