Owen Dolen Recreation Center Roof Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the roof and exterior walls at the Owen Dolen Recreation Center in Owen Dolen Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2013
Projected Completion Date: May 2015
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: December 2018

Construction

Start Date: April 2019
Projected Completion Date: April 2020
Completion Date: August 2020

Understand how we build parks.

Funding

Total Funding: $1,759,000
Funding Sources:
  • Borough President
  • City Council

Location

Owen F. Dolen Park, Bronx
2551 Westchester Avenue
Community Board: 10

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project