Ferry Point Park Synthetic Turf Soccer Field 1 Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct synthetic turf soccer field 1 at Ferry Point Park, which was damaged by Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2013
Projected Completion Date:
December 2014
Completion Date:
March 2015
Procurement
Start Date: March 2015
Projected Completion Date:
December 2015
Completion
Date:
April 2016
Construction
Start Date: May 2016
Projected Completion Date:
May 2017
Completion Date: January 2017
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Ferry Point Park, Bronx
Schley Avenue and Hutchinson River Parkway
Community Board: 10
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024