Citywide Retaining Walls and Seawalls Reconstruction (CNYG-514M)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct and stabilize retaining walls and seawalls in parks citywide.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2013
Projected Completion Date: December 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: May 2015

Construction

Start Date: May 2015
Projected Completion Date: November 2017
Completion Date: February 2020

Understand how we build parks.

Funding

Total Funding: $26,207,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • Alley Pond Park, Queens
    West of Cross Island Parkway from 46th Avenue to LIE
    Community Board: 11
  • Carl Schurz Park, Manhattan
    East End Avenue to East River, East 84 to East 90 Streets
    Community Board: 08
  • Clove Lakes Park, Staten Island
    Slosson Avenue, Victory Boulevard, Clove Road
    Community Board: 01
  • East River Esplanade, Manhattan
    FDR Drive, East 90 to East 125 Streets
    Community Board: 08, 11
  • Forest Park, Queens
    Myrtle Ave., Union Turnpike, Park Lane South bet. Brooklyn-Queens County Line and Park Lane
    Community Board: 05, 05, 06, 09
  • Fort Totten Park, Queens
    Fort Totten, Cross Island Parkway, Totten Road to 15 Road
    Community Board: 07
  • Fort Tryon Park, Manhattan
    Riverside Drive to Broadway, West 192 to Dyckman Streets
    Community Board: 12
  • Inwood Hill Park, Manhattan
    Dyckman St, Hudson River, Harlem River S
    Community Board: 12
  • Riverside Park, Manhattan
    Riverside Drive to Hudson River, West 59 Street to Clair Place
    Community Board: 07, 09
  • Shore Park and Parkway, Brooklyn
    Harbor View to 92nd Street
    Community Board: 10
  • The Battery, Manhattan
    Battery Place, State & Whitehall Street
    Community Board: 01
  • Williamsbridge Oval, Bronx
    Van Cortlandt Avenue East, Bainbridge Avenue, Reservoir Oval
    Community Board: 07
 