Citywide Retaining Walls and Seawalls Reconstruction (CNYG-514M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct and stabilize retaining walls and seawalls in parks citywide.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2013
Projected Completion Date:
December 2013
Completion Date:
January 2014
Procurement
Start Date: January 2014
Projected Completion Date:
October 2014
Completion
Date:
May 2015
Construction
Start Date: May 2015
Projected Completion Date:
November 2017
Completion Date: February 2020
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Mayoral
Locations
-
Alley Pond Park, Queens
West of Cross Island Parkway from 46th Avenue to LIE
Community Board: 11 -
Carl Schurz Park, Manhattan
East End Avenue to East River, East 84 to East 90 Streets
Community Board: 08 -
Clove Lakes Park, Staten Island
Slosson Avenue, Victory Boulevard, Clove Road
Community Board: 01 -
East River Esplanade, Manhattan
FDR Drive, East 90 to East 125 Streets
Community Board: 08, 11 -
Forest Park, Queens
Myrtle Ave., Union Turnpike, Park Lane South bet. Brooklyn-Queens County Line and Park Lane
Community Board: 05, 05, 06, 09 -
Fort Totten Park, Queens
Fort Totten, Cross Island Parkway, Totten Road to 15 Road
Community Board: 07 -
Fort Tryon Park, Manhattan
Riverside Drive to Broadway, West 192 to Dyckman Streets
Community Board: 12 -
Inwood Hill Park, Manhattan
Dyckman St, Hudson River, Harlem River S
Community Board: 12 -
Riverside Park, Manhattan
Riverside Drive to Hudson River, West 59 Street to Clair Place
Community Board: 07, 09 -
Shore Park and Parkway, Brooklyn
Harbor View to 92nd Street
Community Board: 10 -
The Battery, Manhattan
Battery Place, State & Whitehall Street
Community Board: 01 -
Williamsbridge Oval, Bronx
Van Cortlandt Avenue East, Bainbridge Avenue, Reservoir Oval
Community Board: 07
Project Staff
Project Liaison: Contact Us
Contact NYC Parks
about this project
Last updated: 11/22/2024