Dr. John's Playground Paths, Water Supply & Drainage System Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the paths, water supply and drainage systems at Dr. John's Playground.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2011
Projected Completion Date:
October 2014
Completion Date:
January 2016
Procurement
Start Date: January 2016
Projected Completion Date:
October 2016
Completion
Date:
December 2016
Construction
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date: April 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
Marine Park, Brooklyn
Gerritsen Avenue and Avenue X
Community Board: 15, 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024