Glenwood Playground Synthetic Turf Field Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a multi-use synthetic turf field, adult fitness area, and sitting area, and reconstruct the handball courts and basketball courts at Glenwood Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2012
Projected Completion Date: April 2015
Completion Date: June 2015

Procurement

Start Date: June 2015
Projected Completion Date: March 2016
Completion Date: January 2016

Construction

Start Date: April 2016
Projected Completion Date: April 2017
Completion Date: April 2017

Understand how we build parks.

Funding

Total Funding: $1,441,000
Funding Sources:
  • Borough President
  • City Council

Location

Glenwood Playground, Brooklyn
Farragut Road and Ralph Avenue
Community Board: 18

 