Lincoln Terrace Park Netball Court and Seth Low Playground Athletic Court Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the netball and handball courts at Lincoln Terrace Park and the perimeter paths, basketball and handball courts at Seth Low Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2013
Projected Completion Date: November 2013
Completion Date: June 2014

Procurement

Start Date: June 2014
Projected Completion Date: March 2015
Completion Date: June 2015

Construction

Start Date: August 2015
Projected Completion Date: August 2016
Completion Date: August 2016

Understand how we build parks.

Funding

Total Funding: $2,335,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project