Schmul Park and Dugan Playground Ballfield Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the ballfields in Dugan Playground and Schmul Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2013
Projected Completion Date: May 2014
Completion Date: July 2014

Procurement

Start Date: July 2014
Projected Completion Date: April 2015
Completion Date: January 2016

Construction

Start Date: March 2016
Projected Completion Date: September 2017
Completion Date: June 2017

Understand how we build parks.

Funding

Total Funding: $1,538,000
Funding Sources:
  • City Council
  • Federal
  • Mayoral

Locations

  • Gerard P. Dugan Playground, Staten Island
    Mill Rd. to Weed Ave. between Tysens La. and Isernia Ave.
    Community Board: 03
  • Schmul Park, Staten Island
    Wild Ave., Pearson St., Melvin Ave.
    Community Board: 02
 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024