Schmul Park and Dugan Playground Ballfield Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the ballfields in Dugan Playground and Schmul Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: November 2013
Projected Completion Date:
May 2014
Completion Date:
July 2014
Procurement
Start Date: July 2014
Projected Completion Date:
April 2015
Completion
Date:
January 2016
Construction
Start Date: March 2016
Projected Completion Date:
September 2017
Completion Date: June 2017
Understand how we build parks.
Funding
Funding Sources:
- City Council
- Federal
- Mayoral
Locations
-
Gerard P. Dugan Playground, Staten Island
Mill Rd. to Weed Ave. between Tysens La. and Isernia Ave.
Community Board: 03 -
Schmul Park, Staten Island
Wild Ave., Pearson St., Melvin Ave.
Community Board: 02
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025