Queensbridge Park Field House Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a field house in Queensbridge Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2014
Projected Completion Date:
March 2016
Completion Date:
February 2017
Procurement
Start Date: February 2017
Projected Completion Date:
November 2017
Completion
Date:
December 2017
Construction
Start Date: January 2018
Projected Completion Date:
July 2019
Completion Date: March 2020