Queensbridge Park Field House Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a field house in Queensbridge Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2014
Projected Completion Date: March 2016
Completion Date: February 2017

Procurement

Start Date: February 2017
Projected Completion Date: November 2017
Completion Date: December 2017

Construction

Start Date: January 2018
Projected Completion Date: July 2019
Completion Date: March 2020

Understand how we build parks.

Funding

Total Funding: $6,378,000
Funding Sources:
  • City Council
  • Mayoral

Location

Queensbridge Park, Queens
Vernon Boulevard between the Queensboro Bridge and 41st Avenue
Community Board: 01, 02

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 01/17/2025