Hendrick I. Lott House Interior Restoration
-
50% complete
-
0% complete
-
0% complete
This project will restore the interior of the Hendrick I. Lott House.
Project Notes
Project Update: Parks is continuing to develop the documents to build this project.
Project Timeline
Design
Assigned & Start Date: August 2023
Projected Completion Date:
January 2025
Procurement
The average time for procurement is 9-12 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Understand how we build parks.
Funding
Funding Source: City Council
Location
Hendrick I. Lott House, Brooklyn
1940 East 36th Street
Community Board: 18
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024