DiGilio Playground Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct DiGilio Playground including the play equipment, swings, spray shower, pavement, adult fitness equipment, planting, seating, and game tables.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: August 2013
Projected Completion Date:
September 2014
Completion Date:
December 2015
Procurement
Start Date: December 2015
Projected Completion Date:
August 2016
Completion
Date:
December 2016
Construction
Start Date: April 2017
Projected Completion Date:
April 2018
Completion Date: May 2018
Understand how we build parks.
Funding
Funding Source: City Council
Location
DiGilio Playground, Brooklyn
McDonald Avenue and Avenue F
Community Board: 14
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project