DiGilio Playground Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct DiGilio Playground including the play equipment, swings, spray shower, pavement, adult fitness equipment, planting, seating, and game tables.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: August 2013
Projected Completion Date: September 2014
Completion Date: December 2015

Procurement

Start Date: December 2015
Projected Completion Date: August 2016
Completion Date: December 2016

Construction

Start Date: April 2017
Projected Completion Date: April 2018
Completion Date: May 2018

Understand how we build parks.

Funding

Total Funding: $2,856,000
Funding Source: City Council

Location

DiGilio Playground, Brooklyn
McDonald Avenue and Avenue F
Community Board: 14

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 10/11/2024