Second Avenue Subway Street Tree Planting Restitution for Removed Trees

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant street trees in Community Boards 5, 6, 8, 10 and 11 in Manhattan as restitution for trees removed for the Second Avenue Subway construction.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2013
Projected Completion Date: December 2013
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: May 2015

Construction

Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $1,322,000
Funding Source: Private