  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new street trees as restitution for the Yankee Stadium construction.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2013
Projected Completion Date: December 2013
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: April 2015

Construction

Start Date: April 2015
Projected Completion Date: April 2016
Completion Date: July 2016

Understand how we build parks.

Funding

Total Funding: $2,165,000
Funding Sources:
  • City Council
  • Mayoral

Location

Various locations, citywide