Joyce Kilmer Park Perimeter Fence Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a steel perimeter fence in Joyce Kilmer Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: November 2013
Projected Completion Date: June 2014
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: February 2017

Construction

Start Date: March 2017
Projected Completion Date: March 2018
Completion Date: March 2018

Understand how we build parks.

Funding

Total Funding: $737,000
Funding Sources:
  • Borough President
  • City Council
  • Federal

Location

Joyce Kilmer Park, Bronx
Grand Concourse between East 161st and East 164th Streets
Community Board: 04

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 01/17/2025