Pelham Bay Park Ballfields 4 & 5 Lighting Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the electrical feeders and conduits at ballfields 4 and 5 in Pelham Bay Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2013
Projected Completion Date: March 2014
Completion Date: October 2014

Procurement

Start Date: October 2014
Projected Completion Date: June 2015
Completion Date: August 2015

Construction

Start Date: January 2016
Projected Completion Date: January 2017
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $875,000
Funding Source: Mayoral

Location

Pelham Bay Park, Bronx
Middletown Road and Bruckner Boulevard
Community Board: 10, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024