Crotona Parkway Green Infrastructure Construction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct a stormwater greenstreet on Crotona Parkway between East 178th Street and East Tremont Avenue.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: September 2013
Projected Completion Date: November 2013
Completion Date: November 2013

Procurement

Start Date: November 2013
Projected Completion Date: August 2014
Completion Date: October 2014

Construction

Start Date: October 2014
Projected Completion Date: July 2015
Completion Date: June 2015

Understand how we build parks.

Funding

Total Funding: $294,000
Funding Sources:
  • Mayoral
  • Private

Location

Crotona Parkway Malls, Bronx
East 178th Street and East Tremont Avenue
Community Board: 03, 06

 

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024