Crotona Parkway Green Infrastructure Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct a stormwater greenstreet on Crotona Parkway between East 178th Street and East Tremont Avenue.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: September 2013
Projected Completion Date:
November 2013
Completion Date:
November 2013
Procurement
Start Date: November 2013
Projected Completion Date:
August 2014
Completion
Date:
October 2014
Construction
Start Date: October 2014
Projected Completion Date:
July 2015
Completion Date: June 2015
Understand how we build parks.
Funding
Funding Sources:
- Mayoral
- Private
Location
Crotona Parkway Malls, Bronx
East 178th Street and East Tremont Avenue
Community Board: 03, 06
Project Staff
Contact NYC Parks about this projectLast updated: 11/22/2024