Midland Beach and Oakwood Beach Emergency Berm Installation
-
100% complete
-
100% complete
-
100% complete
This project will construct a temporary emergency protective berm at Midland Beach from New Dorp Lane to Ocean Breeze Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2013
Completion Date:
October 2013
Procurement
Start Date: October 2013
Projected Completion Date:
July 2014
Completion
Date:
March 2014
Construction
Start Date: November 2013
Projected Completion Date:
February 2014
Completion Date: April 2014
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Franklin D. Roosevelt Boardwalk and Beach, Staten Island
Between Graham Boulevard, Jefferson Avenue, Father Capodanno Boulevard
Community Board: 02 -
Great Kills Park, Staten Island
East of Cedar Grove Avenue, between New Dorp Lane and Kissam Avenue. (New Dorp Beach, Cedar Grove Beach and Oakwood Beach)
Community Board: 03
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025