Riverside Park and Fort Washington Park Pathway Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct paths, pavements, and general site work in Riverside Park South, Riverside Park and Fort Washington Park in Manhattan, which were damaged by Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2013
Projected Completion Date:
January 2014
Completion Date:
June 2018
Procurement
Start Date: June 2018
Projected Completion Date:
March 2019
Completion
Date:
June 2019
Construction
Start Date: October 2019
Projected Completion Date:
October 2020
Completion Date: November 2020
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Fort Washington Park, Manhattan
Riverside Drive, Hudson River, West 155 - West 179 Streets, Henry Hudson Parkway
Community Board: 12 -
Riverside Park, Manhattan
Riverside Drive to Hudson River, West 59 Street to Clair Place
Community Board: 07, 09 -
Riverside Park South, Manhattan
Riverside Drive between 65 Street and 72 Street
Community Board: 07
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 11/22/2024