Vietnam Veterans Plaza Reconstruction (Hurricane Sandy)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct lighting and electrical components damaged by Hurricane Sandy at Vietnam Veterans Plaza.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: June 2015
Projected Completion Date:
June 2016
Completion Date:
February 2019
Procurement
Start Date: February 2019
Projected Completion Date:
October 2019
Completion
Date:
June 2022
Construction
Start Date: July 2022
Projected Completion Date:
July 2023
Completion Date: July 2023
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Vietnam Veterans Plaza, Manhattan
South Street between Broad Street and Old Slip