Project Timeline
Design
Assigned & Start Date: August 2012
Projected Completion Date:
July 2013
Completion Date:
December 2013
Procurement
Start Date: December 2013
Projected Completion Date:
September 2014
Completion
Date:
June 2015
Construction
Start Date: August 2015
Projected Completion Date:
August 2016
Completion Date: August 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Locations
-
Colonel David Marcus Playground, Brooklyn
Ave. P bet. E. 4 St. and Ocean Pkwy.
Community Board: 12 -
Jackie Robinson Playground, Brooklyn
Sullivan Pl, Franklin Av, Montgomery St
Community Board: 09
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024