Tappen Park and South Beach Fountain Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the electrical and mechanical components of fountains damaged during Hurricane Sandy at Tappen Park and South Beach.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2015
Projected Completion Date:
June 2016
Completion Date:
June 2017
Procurement
Start Date: June 2017
Projected Completion Date:
March 2018
Completion
Date:
February 2020
Construction
Start Date: September 2020
Projected Completion Date:
September 2021
Completion Date: May 2022
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Franklin D. Roosevelt Boardwalk and Beach, Staten Island
Father Capodanno Boulevard, Boardwalk, Doty, Avenue, Sea Gate Court
Community Board: 02 -
Tappen Park, Staten Island
Canal Street, Wright to Bay Streets
Community Board: 01
Project Staff
Project Liaison: Joseph Homsey
Contact NYC Parks
about this project
Last updated: 01/17/2025