Ralph Demarco Park Shoreline Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    90% complete

This project will reconstruct the shoreline damaged by Hurricane Sandy in Ralph Demarco Park.

Project Notes

Due to COVID related impacts, this project may have experienced schedule delays.

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2016
Projected Completion Date: September 2017
Completion Date: October 2020

Procurement

Start Date: October 2020
Projected Completion Date: July 2021
Completion Date: April 2023

Construction

Start Date: October 2023
Projected Completion Date: October 2024

Understand how we build parks.

Funding

Total Funding: $7,734,000
Funding Sources:
  • Federal
  • Mayoral

Location

Ralph Demarco Park, Queens
East River, Shore Boulevard, Ditmars Boulevard, 20th Avenue
Community Board: 01

 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project

Last updated: 11/22/2024