Conference House Park Path, Rail, and Landscape Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Hurricane Sandy-damaged paths, the overlook and the parking lot in Conference House Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2015
Projected Completion Date: June 2016
Completion Date: January 2017

Procurement

Start Date: January 2017
Projected Completion Date: October 2017
Completion Date: May 2018

Construction

Start Date: June 2018
Projected Completion Date: June 2019
Completion Date: January 2019

Understand how we build parks.

Funding

Total Funding: $448,000
Funding Sources:
  • Federal
  • Mayoral

Location

Conference House Park, Staten Island
Page Avenue between Raritan Bay and Hylan Boulevard
Community Board: 03

 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 01/17/2025