Brooklyn General Site Work For Hurricane Sandy (BG-1113M)
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct play equipment, safety surfacing, athletic fields, pavements, fencing, and masonry at various parks in Brooklyn that were damaged by Hurricane Sandy.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: April 2013
Projected Completion Date:
July 2013
Completion Date:
June 2014
Procurement
Start Date: June 2014
Projected Completion Date:
March 2015
Completion
Date:
June 2015
Construction
Start Date: July 2015
Projected Completion Date:
January 2017
Completion Date: December 2016
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Locations
-
Brighton Playground, Brooklyn
Brighton 2nd Street & Boardwalk
Community Board: 13 -
Carroll Park, Brooklyn
Court St., Smith St., bet. Carroll St. and President St.
Community Board: 06 -
Coffey Park, Brooklyn
Verona St. bet. Richard St. and Dwight St.
Community Board: 06 -
McGuire Fields, Brooklyn
Ave Y., Bergen Ave. bet. Ave. V and Belt Pkwy.
Community Board: 18 -
Nautilus Playground, Brooklyn
Public Beach, W 29 and W 32 Sts
Community Board: 13 -
Ocean Parkway Malls, Brooklyn
Park Circle To Coney Island Concourse
Community Board: 07, 12, 13, 14, 15
Project Staff
Project Liaison: Davey Ives
Contact NYC Parks
about this project
Last updated: 11/22/2024