Pelham Bay Park Adult Fitness Equipment and Nature Walk Construction
-
100% complete
-
100% complete
-
100% complete
This project will construct an adult fitness area and nature walk in Pelham Bay Park.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: July 2013
Projected Completion Date:
February 2015
Completion Date:
May 2015
Procurement
Start Date: May 2015
Projected Completion Date:
February 2016
Completion
Date:
February 2016
Construction
Start Date: March 2016
Projected Completion Date:
June 2017
Completion Date: August 2017
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
- Mayoral
Location
Pelham Bay Park, Bronx
Middletown Road between Bruckner Boulevard and Stadium Avenue
Community Board: 10, 12
Project Staff
Project Liaison: Katerine Borrome
Contact NYC Parks
about this project
Last updated: 11/22/2024