Bronx River Park 233rd Street Bikeway Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the paths, landscape and staircase at East 233rd Street in Bronx River Park.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2012
Projected Completion Date: April 2014
Completion Date: August 2015

Procurement

Start Date: August 2015
Projected Completion Date: May 2016
Completion Date: October 2016

Construction

Start Date: November 2016
Projected Completion Date: January 2018
Completion Date: May 2019

Understand how we build parks.

Funding

Total Funding: $2,323,000
Funding Source: Mayoral

Location

Bronx River Parkway, Bronx
East 233rd Street and the Bronx River
Community Board: 06, 09, 12

 

Project Staff

Project Liaison: Katerine Borrome
Contact NYC Parks about this project

Last updated: 11/22/2024