North 5th Street Pier and Park Bulkhead Reconstruction (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the bulkhead at North 5th Street Pier and Park, which was damaged by Hurricane Sandy.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2013
Projected Completion Date: June 2014
Completion Date: January 2016

Procurement

Start Date: January 2016
Projected Completion Date: October 2016
Completion Date: March 2017

Construction

Start Date: October 2017
Projected Completion Date: October 2018
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $1,912,000
Funding Sources:
  • Federal
  • Mayoral

Location

North 5th Street Pier and Park, Brooklyn
Kent Avenue between North 4th Street and North 5th Street
Community Board: 01

 

Project Staff

Project Liaison: Davey Ives
Contact NYC Parks about this project

Last updated: 11/22/2024