Staten Island South Emergency Protective Measures (Hurricane Sandy)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will construct emergency protective measures at Conference House and Crescent Park beaches.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2013
Projected Completion Date: June 2013
Completion Date: January 2014

Procurement

Start Date: January 2014
Projected Completion Date: October 2014
Completion Date: November 2013

Construction

Start Date: August 2013
Projected Completion Date: October 2013
Completion Date: December 2013

Understand how we build parks.

Funding

Total Funding: $2,957,000
Funding Sources:
  • Federal
  • Mayoral

Locations

  • Conference House Park, Staten Island
    Pittsville St., Hylan Blvd. Richard Ave.
    Community Board: 03
  • Crescent Beach Park, Staten Island
    Tennyson Dr. between Hales Ave. and Wiman Ave.
    Community Board: 03
 

Project Staff

Project Liaison: Joseph Homsey
Contact NYC Parks about this project

Last updated: 10/11/2024