Dunningham Triangle and Playground Ninety Basketball Court and Spray Shower Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct Dunningham Triangle and the basketball court and spray shower at Playground Ninety.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: December 2012
Projected Completion Date: August 2013
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: June 2015

Construction

Start Date: July 2015
Projected Completion Date: December 2016
Completion Date: June 2016

Understand how we build parks.

Funding

Total Funding: $562,000
Funding Sources:
  • Borough President
  • City Council

Locations

  • Dunningham Triangle, Queens
    82nd Street, Baxter Avenue to Ithaca Street
    Community Board: 04
  • Playground Ninety, Queens
    90th Street between Northern Boulevard & 32 Avenue
    Community Board: 03
 

Project Staff

Project Liaison: Meira Berkower
Contact NYC Parks about this project