Queens General Site Work (QG-1813M)
-
100% complete
-
100% complete
-
100% complete
This multisite contract will reconstruct pavements, fencing, water supply, plantings and general site work in Queens.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: May 2013
Projected Completion Date:
August 2013
Completion Date:
August 2013
Procurement
Start Date: August 2013
Projected Completion Date:
May 2014
Completion
Date:
May 2014
Construction
Start Date: October 2014
Projected Completion Date:
September 2015
Completion Date: January 2016
Understand how we build parks.
Funding
Funding Sources:
- Borough President
- City Council
Locations
-
College Point Park, Queens
14 Ave. bet. 121 St. and College Point Blvd.
Community Board: 07 -
Plaut Triangle, Queens
Northern Blvd., 43 Ave. bet. 169 St. and 170 St.
Community Board: 07
Project Staff
Project Liaison: Meira Berkower