Riverside Drive Bus Stop and Safety Measure Installation

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the bus stops and perimeter sidewalks along Riverside Drive.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: July 2015
Projected Completion Date: March 2015
Completion Date: October 2017

Procurement

Start Date: October 2017
Projected Completion Date: July 2018
Completion Date: January 2019

Construction

Start Date: March 2019
Projected Completion Date: May 2020
Completion Date: October 2020

Understand how we build parks.

Funding

Total Funding: $2,729,000
Funding Sources:
  • Borough President
  • Federal
  • Mayoral

Location

Riverside Park, Manhattan
Riverside Drive between West 97th Street and West 125th Street
Community Board: 07, 09

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 11/22/2024