Project Timeline
Design
Assigned & Start Date: April 2013
Projected Completion Date:
May 2013
Completion Date:
June 2013
Procurement
Start Date: June 2013
Projected Completion Date:
March 2014
Completion
Date:
February 2014
Construction
Start Date: March 2014
Projected Completion Date:
March 2015
Completion Date: March 2015