Brooklyn Street Tree Planting FY14 - Community Boards 7,10-15

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant street trees in Community Boards 7, and 10 through 15 in Brooklyn.

Project Timeline

Design

Assigned & Start Date: April 2013
Projected Completion Date: May 2013
Completion Date: June 2013

Procurement

Start Date: June 2013
Projected Completion Date: March 2014
Completion Date: February 2014

Construction

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: March 2015

Understand how we build parks.

Funding

Total Funding: $2,695,000
Funding Sources:
  • Borough President
  • Mayoral

Location

Various locations, Brooklyn

Project Staff

Contact NYC Parks about this project

Last updated: 11/22/2024