Queens Street Tree Planting FY14 - Community Boards 7-9,11

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant new street trees in Community Boards 7, 8, 9 and 11 in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2013
Projected Completion Date: May 2013
Completion Date: June 2013

Procurement

Start Date: June 2013
Projected Completion Date: March 2014
Completion Date: February 2014

Construction

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: May 2015

Understand how we build parks.

Funding

Total Funding: $1,307,000
Funding Source: Mayoral

Location

Various locations, Queens