Asser Levy Recreation Center Boiler and Pool Dehumidifier Reconstruction
-
100% complete
-
100% complete
-
100% complete
This project will reconstruct the boiler and pool dehumidification system at Asser Levy Recreation Center.
Project Notes
The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.
Project Timeline
Design
Assigned & Start Date: October 2012
Projected Completion Date:
August 2013
Completion Date:
December 2013
Procurement
Start Date: December 2013
Projected Completion Date:
August 2014
Completion
Date:
January 2015
Construction
Start Date: February 2015
Projected Completion Date:
February 2016
Completion Date: May 2017
Understand how we build parks.
Funding
Funding Sources:
- Federal
- Mayoral
Location
Asser Levy Playground, Manhattan
Asser Levy Place between East 23rd Street and East 25th Street
Community Board: 06
Project Staff
Project Liaison: Steve Simon
Contact NYC Parks
about this project
Last updated: 01/17/2025