Asser Levy Recreation Center Boiler and Pool Dehumidifier Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the boiler and pool dehumidification system at Asser Levy Recreation Center.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: October 2012
Projected Completion Date: August 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: August 2014
Completion Date: January 2015

Construction

Start Date: February 2015
Projected Completion Date: February 2016
Completion Date: May 2017

Understand how we build parks.

Funding

Total Funding: $1,384,000
Funding Sources:
  • Federal
  • Mayoral

Location

Asser Levy Playground, Manhattan
Asser Levy Place between East 23rd Street and East 25th Street
Community Board: 06

 

Project Staff

Project Liaison: Steve Simon
Contact NYC Parks about this project

Last updated: 01/17/2025