Queens Street Tree Planting FY14 - Community Boards 10,12-14

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will plant trees in Community Boards 10, 12, 13 and 14 in Queens.

Project Timeline

Design

Assigned & Start Date: April 2013
Projected Completion Date: May 2013
Completion Date: June 2013

Procurement

Start Date: June 2013
Projected Completion Date: March 2014
Completion Date: February 2014

Construction

Start Date: March 2014
Projected Completion Date: March 2015
Completion Date: February 2015

Understand how we build parks.

Funding

Total Funding: $1,341,000
Funding Source: Mayoral

Location

Various locations, Queens

Project Staff

Contact NYC Parks about this project