Queens General Public Restroom Building and Facility Reconstruction (QG-1513MA1)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct public restroom buildings and facilities at various parks and recreation locations in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: May 2013
Projected Completion Date: May 2013
Completion Date: July 2015

Procurement

Start Date: July 2015
Projected Completion Date: April 2016
Completion Date: March 2017

Construction

Start Date: April 2017
Projected Completion Date: April 2019
Completion Date: September 2018

Understand how we build parks.

Funding

Total Funding: $1,470,000
Funding Sources:
  • Borough President
  • City Council
  • Mayoral

Locations

 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025