Queens General Public Restroom Building and Facility Reconstruction (QG-1613MA)

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct public restroom buildings and facilities at various parks and recreation locations in Queens.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: April 2013
Projected Completion Date: May 2013
Completion Date: August 2014

Procurement

Start Date: August 2014
Projected Completion Date: May 2015
Completion Date: December 2016

Construction

Start Date: March 2017
Projected Completion Date: March 2019
Completion Date: June 2018

Understand how we build parks.

Funding

Total Funding: $1,668,000
Funding Sources:
  • City Council
  • Mayoral

Locations

  • Helen Marshall Playground, Queens
    25 Av Bet 98 and 100 Sts
    Community Board: 03
  • Kissena Park, Queens
    Fresh Meadows La., Kissena Blvd., bet. Oak Ave., Underhill., and Booth Memorial Ave.
    Community Board: 07
 

Project Staff

Project Liaison: Cristin Leoutsakos
Contact NYC Parks about this project

Last updated: 01/17/2025