O'Connell Playground Recreation Building Reconstruction

  • Design
    100% complete
  • Procurement
    100% complete
  • Construction
    100% complete

This project will reconstruct the recreation building in Daniel M. O'Connell Playground.

Project Notes

The completion date has changed. To learn more about why schedules change, please visit the How We Build Parks page.

Project Timeline

Design

Assigned & Start Date: March 2013
Projected Completion Date: May 2013
Completion Date: December 2013

Procurement

Start Date: December 2013
Projected Completion Date: September 2014
Completion Date: December 2018

Construction

Start Date: October 2018
Projected Completion Date: April 2019
Completion Date: April 2019

Understand how we build parks.

Funding

Total Funding: $2,053,000
Funding Sources:
  • City Council
  • Mayoral

Location

Daniel M. O'Connell Playground, Queens
Murdock Avenue, 113th Avenues, 196th Street, 197th Street
Community Board: 12

 